Main switch cabinets
September 2023
We have commenced the construction of main switchgear cabinets for a crane pontoon with an electric crane. Soon, we will gladly share more updates about this project and showcase the final result.
November 2023
The cabinets are nearly ready, which means we can soon start their installation on board the crane pontoon. During this period, we will keep you regularly updated on the installation progress on the crane pontoon.
December 2023
Meanwhile, we have begun work on the crane pontoon. The main switchgear cabinets have been hoisted on board and will be connected in the coming weeks. The cabling in the lower part of the pontoon has been laid, and the upcoming period will mainly focus on connecting and carrying out other tasks on board.
January 2024
The cabinets on board the pontoon are nearly all connected by now.